The building is divided into two sections A and B. Section A, the east end, is ahead of section B, the west end.
*This week the windows will be installed in section A of the building.
*Steel trusses will be erected this week in the gym/cafeteria.
*Pouring concrete floor on 2nd floor and Media center this week
*Mason is still ongoing in section B (Kindergarten rooms), projected to be done in 4-6 weeks depending on weather.
*Projected completion date is August